The EOQ is 980 units and should reduce the fixed ordering cost to an amount of $62.50.
<u>Explanation:</u>
a)
Annual demand=Qty per mth multiply with 12 = 1000 multiply with 12 =12000
Annual demand in USD, A= 12000 multiply with USD 100 (cost of each part) = USD 1200000
Preparation cost, P= 4 hrs changeover time multiply with USD 250 per hr = USD 1000
Annual holding cost, I = 25% = 0.25
EOQ in USD= Root over (2 multiply with A multiply with P divide by I ) = USD 9.79 multiply with 10000 = USD 98000
EOQ in nos. = USD 98000 divide by USD 100 (cos of each part) = 980 units
b) Q = 980 divide by 4 = 245
In this case, annual carryring cost, C = EOQ 980 by 4 multiply with 0.5 multiply with Unit cost USD 100 multiply with 0.25 = USD 3062.50
Annual demand, D = 1000 per month multiply with 12 = 12000
Ordering cost = C multiply with 245 / D = USD 62.50
Answer[:]
It is basically the side of a rectangle, and the adjacent side extended outward. There are pictures below.
[:] DustinBR [:]
What do you mean 18, but not older than 18?
The statement of work is <span>a contract that defines the tasks, time frame, and deliverables that a vendor must perform for a client.
There are several things that will be written in the statement of work in order to manage the deal, such as the name of the project, the timeline for the project, the project handler, the delivery method, etc.</span>
Answer:
Explanation:
Opening units 0
Started 56000
56000
Transffered 30000
Closing 26000
Production Table
Using Weighted Average Method
Cost Element Complete Closing WIP Equivellant production units
Material 30,000 26,000 56,000
Labour Cost 30,000 19,500 49,500