1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Lyrx [107]
2 years ago
7

If a subdivision has fewer than five parcels, the developer only needs to file a?

Computers and Technology
1 answer:
Over [174]2 years ago
6 0

If a subdivision has fewer than five parcels, the developer only needs to file a parcel map.

<h3>What is a Parcel map?</h3>

A parcel map may be defined as a type of map that significantly represents the subdivision of land into Parcels for sale and is recorded in the County Recorder's Office.

Parcel Maps generally contain fewer or more than Tract Maps and it basically requires improvements that are less extensive than tract Maps.

Parcel maps are typically regulated at a variety of measures and can be either very precise or very general which show only schematic layouts of the basic land portion.

Therefore, if a subdivision has fewer than five parcels, the developer only needs to file a parcel map.

To learn more about Parcel map, refer to the link:

brainly.com/question/4493398

#SPJ4

You might be interested in
Plz I need the answer!!!:(
dimaraw [331]

Answer:

Procedural, Visual, Logic - Based

Explanation:

7 0
3 years ago
A computer has __________processing device
Artist 52 [7]

Answer:

electronic processing device

4 0
3 years ago
1.03!! need help!! kinda hard!!
dexar [7]
I think it’s internet sorry if it’s wrong
5 0
3 years ago
Which of the following is the estimate of the minimum amount of time it would take to perform a task? (Points : 2) Minimal durat
kondor19780726 [428]

Answer:

Optimistic duration

Explanation:

The following three concepts are Project management concepts:

Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.

Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc

Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.

Which of the following is the estimate of the minimum amount of time it would take to perform a task?

The answer is Optimistic duration

7 0
3 years ago
What does Joann need to change in her outline?
Alona [7]
Where’s the outline?
6 0
3 years ago
Read 2 more answers
Other questions:
  • The memory locations listed in a procedure header's parameterList have procedure scope and are removed from the computer's main
    9·1 answer
  • Short Answer: Computer models and simulations are used to formulate, refine, and test hypotheses. Describe a scenario that could
    8·1 answer
  • Felicia has been having problems with her computer. Her documents won’t open, her computer is running slow, and programs automat
    7·1 answer
  • Create a network for a company that sells shoes. Describe the hardware needed and the size of the network (PAN, LAN, WAN) and ma
    6·1 answer
  • Digital Subscriber Line (DSL) is the only Internet connection option available for a small office in the middle of nowhere. Whic
    15·1 answer
  • Dave has to create animations for a game. Which tool can Dave use?
    6·1 answer
  • Access-lists pose a logical problem which often has more than one solution. Can you think of a different set of rules or placeme
    8·1 answer
  • A garments manufacturing company buys various types of natural and synthetic materials to produce clothes. Which material is a s
    6·2 answers
  • Write a method named printGPA that takes in as a parameter a Scanner to read in user input, and calculates a student's grade poi
    8·1 answer
  • In what tab can a user find the workspace option?
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!