Answer:
two words are socialism and communism
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
i think the aswer is (A) <span>Checks are the most widely accepted form of payment.</span>
Answer: False
Explanation:
The contract is such that Molly agreed to bring bracelets if Jean would pay for said bracelets.
The terms of the contract therefore are that Jean would pay and Molly would deliver. Jean then calls Molly and says that they will be unable to pay which means that they are not going to be able to hold up their responsibilities in the contract.
Molly has the right to then cancel the contract because the other party will not be able to perform their obligations and face no repercussion for it.
Answer:
With respect to this lease, for 2018 Ogleby should record interest expense of $57,058 and depreciation expense of $107,225. The right answer is c
Explanation:
According to the given data we have the following:
PV of lease=$750,578
Annual payment=$180,000
Rate of interesr=10%
The interest expense would be calculated as follows:
Interest expense = ( PV of lease - Annual payment ) * Rate of interest
Interest expense = ( $750,578 - $180,000 ) * 10%
Interest expense = $57,058
Therefore, With respect to this lease, for 2018 Ogleby should record interest expense of $57,058 and depreciation expense of $107,225.