Answer:
Option (C) is correct.
Explanation:
Given that,
Actual direct labor hours = 8,200
Actual rate = $12.40 per hour
Original production = 1,100 units
Actual units produced = 1,000
Labor standards = 7.6 hours per completed unit
standard rate = $13.00 per hour
Labor time variance:
= (Standard hours - Actual hours) × Standard rate
= (1,000 × 7.6 - 8,200) × $13
= 7,800 Unfavorable
Answer:
b. Increase by $17,000
Explanation:
For computing the change in the operating income, first we have to determine the cost by make and buy options
Make options:
= Variable cost + fixed cost
= $70 + $60
= $130
Buy options:
= Outside supplier cost + fixed cost × remaining percentage
= $77 + $60 × 60%
= $77 + $36
= $113
So, the difference of cost would be
= $130 - $113
= $17
And, the operating income would be
= Number of units make in each year × cost difference
= 1,000 units × $17
= $17,000
Answer:
Just -in-Time(JIT)
Explanation:
Just in time is a lean manufacturing approach through which Organisation manage inventory in such a way that the supplies are received just at the time it is required, just-in-time is one of the key strategies adopted by Toyota in Japan in order to enhance its Efficiency and ensure that it doesn't take the cost of storing inventories in its operations.
That is true because has most likely asked for higher than the offer.
<span>The answer in the blank is that employment of low-skilled workers increased in July. This is because the rate of the minimum wage increased by July compared to that of June. So there will be more employment process due to the increase of the salary, because more skilled workers wants to grab the opportunity of the increased salary.</span>