Answer:
Please see above
Step-by-step explanation:
I have to right stuff here but the answer is above.
Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Solution:
<u>A few tips...</u>
- Tip-1: If "+" and "-" are multiplied, it gives a result of "-".
- Tip-2: If "-" and "-" are multiplied, it gives a result of "+".
- Tip-3: If "+" and "+" are multiplied, it gives a result of "-".
<u>Changing the sign of the given equation.</u>
- 1.25 + (-0.75)
- => 1.25 - 0.75 [Sign changes according to tip-1.]
This could only mean that the arrow would go to <u>1.25 units forward.</u> Then a second arrow will be drawn to go <u>0.75 units back.</u>
The graph that matches with the above info is Option C.
Answer:
Randomly selected adult has an IQ less than 136 is 0.9641
Step-by-step explanation:
It is given that, it is normal distribution with mean 100 and SD as 20.
So, let's use the formula of z-score
z=
For this problem,
x= 136
Plug in this value into the formula
z-score=
=1.8
Now, use z-score table to find the probability
Find the corresponding value for the row 1.8 and the column 0.00, we do get 0.9641
So, Randomly selected adult has an IQ less than 136 is 0.9641