Answer:
20 days
Step-by-step explanation:
It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.
12 * 5 = 60
60/3 = 20
It will take 3 men 20 days to do the same job
Answer:
undefine
Step-by-step explanation:
the slope does not show rise over run it just sgow one of them therefore it is undefine
Answer:
The answer is sometimes.
If the two lines have the same slope, then there will be 0 solutions, and if the two lines are the same, then there will be infinite solutions.
Hope this helps!