Answer:
4.82 percent
Explanation:
We use the Rate formula in this question that is shown in the attachment
The NPER is the period of time.
Provided that,
Present value = $1,000 × 101% = $1,010
Assuming figure - Future value or Face value = $1,000
PMT = 1,000 × 7.5% ÷ 2 = $37.5
NPER = 30 years - 6 years = 24 year × 2 = 48 years
The formula is presented below:
= Rate(NPER;PMT;-PV;FV;type)
The present value come in negative
So, after solving this,
1. The pretax cost of debt is 7.41%
2. And, the after tax cost of debt would be
= Pretax cost of debt × ( 1 - tax rate)
= 7.41% × ( 1 - 0.35)
= 4.82%
This will only require tax from our parent or other's because, this is for level of K-12 so it will be tax from people like us. This is what I thought tho.
Answer:
Semi-indirect organizational pattern is the answer.
Explanation:
The paragraph uses a semi-indirect organizational pattern. The purpose of the paragraph is to inform other employees about Renalda's contribution to the organization and that she will be leaving the company while in the end it is directly pointed to Renalda herself.
Answer:
Unsystematic; unsystematic
Explanation:
In the case of the large portfolio, the non-systematic risk that could be attached would have no effect on the total risk of the portfolio
So it is to be expected that the impact should be of non-systematic risk on different kind of stock that could be offset each other in order to remove out the risk to the investor that occurs from the sources of the risk
Answer:
D) Project importance is enhanced by setting authority equal to that of functional departments.
Explanation:
A matrix organization is characterized by, multiple command system and overlapping of command, control and behavioral pattern.
Here, temporary project groups are created so as to handle short term projects. Personnel are drawn from functional department and their activities are controlled and coordinated by a project manager.
Once a project is completed, the structure is disbanded and the personnel return to their original departments i.e functional department.
During the project duration, a person is responsible and reports to two bosses, one being the project manager and secondly to the functional boss. Thus, under such a structure exists dual reporting.
Under matrix structure for project management, the project manager is not allowed to use resources exclusively for the project i.e like in project management. Rather, such a manager is required to share resources with the organization.