Answer:
D.$19.56
Explanation:
The computation of the standard rate per direct labor hour is shown below:
= Basic direct labor rate + payroll tax rate percentage × Basic direct labor rate + fringe benefits per hour
= $12 + $12 × 13% + $6
= $12 + $1.56 + $6
= $19.56
We simply added the basic direct labor rate + payroll tax rate + fringe benefits per hour so that the correct rate per direct labor hour can come
A business will employ seed capital to fund a specific project or activity. It is the capital raised to start working on a new product or business idea.
<h3>What kind of capital is invested in a business?</h3>
The money a company has on hand to cover both its ongoing expenses and potential future expansion is known as capital. Working capital, debt, equity, and trade capital are the four main types of financial resources.
<h3>What kind of business venture capital is that?</h3>
Venture Capital (VC) is a term used to describe funding given by investors to start-up or small businesses that have a high potential for growth. A venture capital fund is a type of private equity funded by institutional and private investors, including investment banks, insurance providers, and pension funds.
To know more about seed capital visit:-
brainly.com/question/10110060
#SPJ1
Answer:
The correct answer is Domestic Stage/First Stage.
Explanation:
In the first stage of the international development of a company, also known as the national stage, the orientation and operation of an organization is based on the local area, its market capacity is limited to the country of origin. However, its managers seek to transcend borders to publicize their products / services globally, initially intervening in some international market to expand their production volume and achieve economies of scale.
Answer:
10 days
Explanation:
The Critical Path Method is a method of managing activities in a project so as to maximize time. In the case of A, B and C activities, since they are connected with the same start-to-start and finish-to-finish, it means that the activities are linked and as such the duration of the project is 10 days since the last activity will take 10 days to finish.
The implication between SS and FF in the activities means that they start up at the same time in the CPM and while activity A ends at 5 days, C proceeds to 10 days.