Answer:
The units started and completed is 59,900 tons
Explanation:
The computation of the number of tons started and completed during October is shown below:
Units Completed = Beginning Work in Process Units Completed + Units started and Completed
74,900 units = 15,000 tons + Units started and Completed
So, the units started and completed is
= 74,900 tons - 15,000 tons
= 59,900 tons
Hence, the units started and completed is 59,900 tons
Answer:
The correct answer is E
Explanation:
ROE termed as or stand as Return on Equity, which is described as the profitability ratio that evaluates the firm ability for generating the profits from its shareholders investment in the company or firm.
The formula to represent ROE is value of Net Income attributable to the equity shareholders.
ROE = Net Income agter Taxes / Shareholders Equity
And there is one more formula which is a disaggregation of ROE into the non- operating as well as operating components, which is as:
ROE = [ROE +(FLEV × Spread)] x NCI
Therefore, option A and C are correct.
The correct answer is; Offer the customer some literature about the product to take with them.
Further Explanation:
If the customer is already using a product that your bank is offering, you can give them some literature such as pamphlets explaining your banks product. It will depend on your banks policy on giving out information to non-customers.
The information that you give the possible customer should include prices and any perks that they may receive for changing banks. In addition to giving the person literature, you can offer to explain your product in more details and the reasons why they should change banks.
Learn more about banking at brainly.com/question/9608829
#LearnwithBrainly
Answer:
$1,498.86
Explanation:
Given that;
Packing of crates per month(u) = 779
Annual carrying cost of 39% of the purchase price per crate
Ordering cost (S) = $27
D = 779 × 12 = $9,348 crates per year
H = 0.39P
H = 0.39 × $12
H = $4.68 crates per year
Total ordering cost = D/Q × S
= ( $9,348 / 779 ) × $27
= $324
Total Holding cost = Q / 2 × H
= ( 779 / 2 ) × $4.68
= $1,822.86
Annual savings = Total holding cost - Total ordering cost
= $1,822.86 - $324
= $1,498.86
The firm would be saving $1,498.86 annually.
In economics, the demand schedule is a table showing the quantity demanded of a good or service at different price levels. The demand schedule can be graphed as a continuous demand curve on a chart where the Y-axis represents price and the X-axis represents quantity.