Answer:
balance of the loan = $4500
correct option is d. $4, 500
Explanation:
given data
cash at the beginning = $15,000
cash receipts = $50,000
cash disbursements = $34, 500
minimum cash balance = $10,000
maintains = $20,000
company owes = $15,000
to find out
balance of the loan
solution
we get here first excess that is
excess = $15,000 + $50,000 - $34, 500
excess = $30500
so used to loan replay will be here as
used to loan replay = $30500 - $20,000
used to loan replay = $10500
so balance of loan will be here
balance of the loan = $15,000 - $10500
balance of the loan = $4500
correct option is d. $4, 500
The question is incomplete. See the attached image for the missing table showing the demand and supply schedule.
Answer/Explanation:
a. Equilibrium price is the price at which Qd = Qs. Hence, equilibrium price = $4, while equilibrium quantity is the quantity demanded at the equilibrium price, i.e. where quantity demanded = quantity supplied. Therefore equilibrium quantity = 8,000
b. At $5, there would be excess quantity supplied, i.e. Qs · Qd = 10,000 · 6,000 = 4,000. Hence, there would be wastage of resources as a result of surplus. This would lead to decrease in price in order to avoid the wastage of resources.
c. At $2, there would be excess quantity demanded, i.e. Qd · Qs = 12,000 · 4,000 = 8,000. This would lead to increase in price as a result of acute shortage in quantity supplied.
Question: The question is incomplete. See the full question below and the answer.
You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):
Contractor Cost Time
A 100 20
B 80 25
C 79 28
D 82 26
The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)
Answer:
See the explanation for the answer and find attached of the graph.
Explanation:
So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.
Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.
So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.
Answer: Generate, define, and evaluate potential marketing actions.
Explanation: In the given case, Wrangler jeans wants to promote their brand and spread their brand awareness in the market by using different advertisements. Thus, they are trying to make some marketing actions.
Therefore, using marketing research to evaluate customer preferences for choosing the best alternative depicts that company is trying to evaluate and define the marketing actions they should be taking in future.