Answer:
<u>Organize the roles, responsibilities, and accountabilities for risk management and risk mitigation. </u>
Explanation:
The seven domains in an IT structure can be identified as:
- User Domain,
- Workstation Domain,
- LAN Domain,
- WAN LAN Domain,
- Remote Access Domain,
- WAN Domain,
- and System / Application Domain
They can be configured as portals for countermeasure failure and intruders, so it is crucial for organizations to look for ways to protect these domains to prevent unauthorized access to private data.
Therefore the relevance of the systematic approach to threats and vulnerabilities, which will assist in organizing the roles, responsibilities and responsibilities for risk management and mitigation.
Answer:
The code is given below with necessary comments for understanding
Explanation:
#Open the input file.
infile = open("numbers.txt", "r")
#Declare and initialize the required variable sum
#to store the sum of integers read from the file.
sum = 0
#Declare and intialize a variable to store the current
#number read from the file in the integer form.
curNum = 0
#Traverse the input file using for loop.
for curLine in infile:
#Assign the number read from the file to the
#variable curNum in the integr form.
curNum = int(curLine)
#Add the numbers read from the file to the
#variable sum to get the sum of all the
#numbers read from the file.
sum += curNum
# Display the value of the variable runsum.
print(sum)
Answer:
vocational school
Explanation:
These vocational schools are institution postsecondary and job training, these schools offer quickly programs, but with the knowledge to work in a company, if we're talking about technology programs we can consider, programming, network administrator, technician.
These institutes are for people like:
- People without work experience
- People want to start a new career
- People want to reenter to the working market
Answer:
Option a
Explanation:
The Critical Path Method is the arrangement of booked exercises that decides the term of the task. These planned exercises must be performed if the venture is to be viewed as a triumph.
Therefore, options b, c, d and e can't be true because:
b. Activities in the Critical Path Method has no or zero slack.
c. The duration of the critical path in CPM determined on the basis of the latest activity and the earliest initiation.
d. The CPM method schedules the activity of the longest duration.