Answer: The minimum score acceptable is 75, Akron has a score of 69 while Boston has a score of 64. The Manager should not consider Boston and Akron, they both have a score below the acceptable score of 75
Explanation:
Score = 0.5 x Raw material + 0.40 x Transport + 0.10 x Labor cost
Akron = 0.5 x (60) + 0.40 x (80) + 0.10 x (70)
Akron = 30 + 32 + 7 = 69
Boston = 0.5 x (70) + 0.4 x (50) + 0.10 x (90)
Boston = 35 + 20 + 9 = 64.
The minimum score acceptable is 75, Akron has a score of 69 while Boston has a score of 64. The Manager should not consider Boston and Akron, they both have a score below the acceptable score of 75
I would say D as the best answer choice.
Answer:
Risk Management Specialist
Explanation:
this is because this person wants to be in a career that analyzie risk for the company which is a fit for Risk Management Specialist
Answer:
B.) $13.00
Explanation:
Assuming Shawn worked for the whole year.
Assuming the year had 52 weeks.
Each week had 40 hours. the year had 40x52 hours
i.e., the Swan worked for 2,080 hours in the year
Total amount earned = $27,040 for , 2,080 hours.
pay per hour = $27,040/2,080
=$13 per hour.
Answer:
$ 2,327.709
Explanation:
Only the principal amount is considered when calculating simple interest. In simple interest, the principal amount remains constant. The formula for simple interest is as I = p x i x t
where I = interest
P = principal amount ...
i= interest rate
t= time
For Diego, p= $7,999, i= 9.7% , t 36 months or 3 years
Diego will pay
I= 7999 x( 9.7/100) x 3
I= 7999 x 0.097 x 3
Diego will pay $ 2,327.709