Answer:
Project S = $672.48
Project L = $11,500
Explanation:
Net Present Value (NPV) Is Calculated by Taking the Present day (Discounted) Value of all future Net Cash flows based on the Business Cost of Capital and Subtracting the Initial Cost of the Investment.
Using a Financial Calculator NPV calculations will be as follows:
Project S
CF0 = ( $11,000)
CF1 = $3,400
CF2 = $3,400
CF3 = $3,400
CF4 = $3,400
CF5 = $3,400
i = 14 %
NPV = $672.48
Project L
CF0 = ( $23,000)
CF1 = $6,900
CF2 = $6,900
CF3 = $6,900
CF4 = $6,900
CF5 = $6,900
i = 14 %
NPV = $11,500.
Answer:
- IFCO for 20x7 as it is reported comparatively in the 20x8 statements = $5,600
- IFCO for 20x8 = $6,800
Explanation:
1) IFCO for 20x7 as it is reported comparatively in the 20x8 statements, should not include the $400 operating income from the component = $6,000 - $400, or $5,600.
2) IFCO for 20x8 should not include the gains resulting from the disposal of the component nor the losses generated by it = $7,000 - $300 + $100 = $6,800