Answer: D.) 1.22
Explanation:
Price in 2010 = €126,000
Price in 2018 = €154,000
Increase = 154,000/126,000
= 1.22
Answer:
£718,607
Explanation:
Annuities are investment opportunities that require an initial settlement and gives a series of returns of a fixed amount for a specific number of periods.
In simple terms, the question requires us to calculate the amount to be paid today (Present Value) of an annuity that pays £80,000 per year for the next 10 years.
To establish the [Present Value of the Annuity, the future Cash Flows must be discounted to the Present Value using the appropriate discount rate. In our case, we will use the annual effective interest rate of 2%.
Present Value = PMT × [ 1 - 1/(1+r)^n ÷ r ]
Where,
PMT = £80,000
n = 10
r = 2%
Therefore,
Present Value = £80,000 × [ 1 - 1 / (1.02) ^ 10 ÷ 0.02]
= £718,606.80 or £718,607
Conclusion :
She be willing to pay £718,607 today for the annuity.
Answer:
A. Pure project A project manager leads personnel from different functional areas = Team members can work on several projects. Duplication of resources is minimized.
B. Functional project Personnel work on a dedicated project team = Team pride, motivation, and commitment are high.
C. Matrix project A team member reports to two bosses = The project is housed within a functional division of the firm.
Explanation:
For A answer, this kind of project management conducts the people, to work on a multitasking way, because they have to accomplish the responsibilities on their functional area as the same that they must accomplished their responsibilities on the project areas. This can minimized the resources for the project but could impact negatively on the compliment of responsibilities because is the same person for two work fronts.
For B answer, if the people can focus their efforts only in the project, that creates more interest on reach the goals efficiently than if the team were distributed on functional and projects departments
For C answer, when the project is developed in a functional division of the firm, you, as a team project member, must report to the project manager and your functional area boss.
Answer:
Option(A) is the correct answer to the given question .
Explanation:
The integer programming problem is also known as the computational optimization or the functionality method that main objective to limits the some or many of the parameters may be integer. The objective of linear optimization problem to make the objective function as well as integer constraints linear .
- The integer programming problem conclusively specify of the optimised solution to the issue of the integral optimisation.
- All the other option are not correct for the linear integer optimization problem because they are not give objective function as well as integer constraints as linear .