![\left(\frac{f}{g} \right)(x)=\frac{f(x)}{g(x)}=\frac{\sqrt{x^{2}-1}}{\sqrt{x-1}}}=\sqrt{\frac{x^{2}-1}{x-1}}=\sqrt{\frac{(x-1)(x+1)}{x-1}}=\boxed{\sqrt{x+1}}](https://tex.z-dn.net/?f=%5Cleft%28%5Cfrac%7Bf%7D%7Bg%7D%20%5Cright%29%28x%29%3D%5Cfrac%7Bf%28x%29%7D%7Bg%28x%29%7D%3D%5Cfrac%7B%5Csqrt%7Bx%5E%7B2%7D-1%7D%7D%7B%5Csqrt%7Bx-1%7D%7D%7D%3D%5Csqrt%7B%5Cfrac%7Bx%5E%7B2%7D-1%7D%7Bx-1%7D%7D%3D%5Csqrt%7B%5Cfrac%7B%28x-1%29%28x%2B1%29%7D%7Bx-1%7D%7D%3D%5Cboxed%7B%5Csqrt%7Bx%2B1%7D%7D)
Answer:
0.1151 = 11.51% probability of completing the project over 20 days.
Step-by-step explanation:
Normal Probability Distribution
Problems of normal distributions can be solved using the z-score formula.
In a set with mean
and standard deviation
, the z-score of a measure X is given by:
The Z-score measures how many standard deviations the measure is from the mean. After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X, that is, the percentile of X. Subtracting 1 by the p-value, we get the probability that the value of the measure is greater than X.
Expected completion time of the project = 22 days.
Variance of project completion time = 2.77
This means that ![\mu = 22, \sigma = \sqrt{2.77}](https://tex.z-dn.net/?f=%5Cmu%20%3D%2022%2C%20%5Csigma%20%3D%20%5Csqrt%7B2.77%7D)
What is the probability of completing the project over 20 days?
This is the p-value of Z when X = 20, so:
![Z = \frac{X - \mu}{\sigma}](https://tex.z-dn.net/?f=Z%20%3D%20%5Cfrac%7BX%20-%20%5Cmu%7D%7B%5Csigma%7D)
![Z = \frac{20 - 22}{\sqrt{2.77}}](https://tex.z-dn.net/?f=Z%20%3D%20%5Cfrac%7B20%20-%2022%7D%7B%5Csqrt%7B2.77%7D%7D)
![Z = -1.2](https://tex.z-dn.net/?f=Z%20%3D%20-1.2)
has a p-value of 0.1151.
0.1151 = 11.51% probability of completing the project over 20 days.