Answer:
C++ code explained below
Explanation:
#include<bits/stdc++.h>
#include <iostream>
using namespace std;
int FiboNR(int n)
{
int max=n+1;
int F[max];
F[0]=0;F[1]=1;
for(int i=2;i<=n;i++)
{
F[i]=F[i-1]+F[i-2];
}
return (F[n]);
}
int FiboR(int n)
{
if(n==0||n==1)
return n;
else
return (FiboR(n-1)+FiboR(n-2));
}
int main()
{
long long int i,f;
double t1,t2;
int n[]={1,5,10,15,20,25,30,35,40,45,50,55,60,65,70,75};
cout<<"Fibonacci time analysis ( recursive vs. non-recursive "<<endl;
cout<<"Integer FiboR(seconds) FiboNR(seconds) Fibo-value"<<endl;
for(i=0;i<16;i++)
{
clock_t begin = clock();
f=FiboR(n[i]);
clock_t end = clock();
t1=double(end-begin); // elapsed time in milli secons
begin = clock();
f=FiboNR(n[i]);
end = clock();
t2=double(end-begin);
cout<<n[i]<<" "<<t1*1.0/CLOCKS_PER_SEC <<" "<<t2*1.0/CLOCKS_PER_SEC <<" "<<f<<endl; //elapsed time in seconds
}
return 0;
}
Answer:
Option C. The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
is the correct answer.
Explanation:
- Critical path is the term used in Project management.
- It can be known by determining the longest stretch for dependent activities and the time required for them to complete.
- A method known as "critical path method" is used for Project modelling.
- All types of projects including aerospace, software projects, engineering or plant maintenance need Critical method analysis for the modeling of project and estimation.
I hope it will help you!
Answer:
Binary to Gray Code Converter
The logical circuit which converts the binary code to equivalent gray code is known as binary to gray code converter. An n-bit gray code can be obtained by reflecting an n-1 bit code about an axis after 2n-1 rows and putting the MSB (Most Significant Bit) of 0 above the axis and the MSB of 1 below the axis.
The 4 bit binary to gray code conversion table is given in attached file.