Answer: A supply schedule is a table that shows the quantity supplied at different prices in the market. A supply curve shows the relationship between quantity supplied and price on a graph.
Explanation: I HOPED THAT HELPED,!
The Answer is D cost and benefit ranked in progressive units.
Answer:
D. 75 days
F) 20+ RANDBETWEEN (-8,8)
B. 60 days
Explanation:
The project has 7 tasks which needs to be completed to finish the project. There are task a and b which can start simultaneously so we will start these two tasks together to reduce the time of the total completion of project. The projects a and b can start at zero = 15 days
using the following equation we calculate days to complete the project.
15ab + 10cde + 20ge + 20fg = 75 days.
Answer: B. Record revenue that will be received in cash in a subsequent period.
Explanation: Accrual Accounting is a method that records transactions when they have inccured. Instead of when the cash is exchanged.
A. Incorrect. Impossible to record in earlier periods. As the past financial statements from previous years have already been closed off.
B. Correct. Accrued accounting entails recording the transaction when it has occurred. So the cash will be recorded as received. However the cash will only be transferred to the revenue account when the obligation has been met. Therefore it will only be transferred to revenue in the period that it applies to.
C. Incorrect. This is already general expense and general accounting rules apply. I.e. The expense is incurred in the same year and paid out in the same year. This is how most income and expenses are treated, except for prepaid and accrual income and expenses.
D. Incorrect. This is an example of a prepaid expense. Prepaid expenses are expenses that have already been paid even though they haven't been inccured yet. This is an asset, and is thus recorded on the debit side.
C) Time-function mapping extends value-stream mapping to include suppliers.