Answer:
6
Step-by-step explanation:
I think its 6 times greater because the length was tripled and the width was doubled thus : 3 * 2 = 6
HOPE THIS HELPED
Q1) £16.50 x 1.12 = £18.48
Q2)
2+9+1= 12
3h 33m = 213m
213/12 = 17.75
2x17.75 = 35.5 (music)
9x17.75 = 159.75 (films)
1x17.75 = 17.75 (books)
So it’s 159.75 minutes for the films to download
Answer: 9,600
Step-by-step explanation:
I could possibly did wrong but I shall explain this none the less. I first knew that 10% of 16,000 was 1,600. So then I just timed that by four getting 6,400. I then did 16,000-6,400 getting $9,600. Sorry if I’m wrong
16 because you divide i hour by 15 and multiply that by 4:)
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.