Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer: Blockbusting
Explanation:
Blockbusting could be defined as when an individual or someone that's into real estate tries to convince a particular set of people(mostly white) living in a neighborhood to sell their property describing to them that those property would soon depreciate in value and this promotes fear in the heart of occupants of those property. Most times the agents do this for their own gain rather than stating the obvious and it's illegal to do. Agent Simpson is practicing blockbusting kind of descrimination.
Answer:
Explanation:
The time (T) = 6 months = 6/12 years = 0.5 years
Interest rate (r) = 6% = 0.06
The stock is priced [S(0)] = $36.50
The price the stock sells at 6 months () = $3.20
European call (K) = $35
The price (P) is given by:
The price of a 6-month, $35.00 strike put option is $1.65
Answer:
Interest payment on bonds payable is a cash outflow from financing activities.
Explanation:
The only statement which is false from the list is : Interest payment on bonds payable is a cash outflow from financing activities.
Interest payment on bonds payable is an expense in the income statement used to determine the income for the year. Net Income falls under the Cash flows from Operating Activities.
Answer:
the expected return on the portfolio is 12.34%
Explanation:
The computation of the expected return on the portfolio is shown below:
Expected Return is
= Investment in BBB × Return+ Investment in ZI × Return
= 16.4 × 48% + 8.6 ×52%
= 7.87% + 4.47%
= 12.34%
hence, the expected return on the portfolio is 12.34%