Answer:
All equity plan:
EPS = $160,000 / 42,000 = $3.81
Plan I:
EPS = [$160,000 - ($108,000 x 7%)] / 39,000 = $152,440 / 39,000 = $3.91
Plan II:
EPS = [$160,000 - ($324,000 x 7%)] / 33,000 = $137,320 / 33,000 = $4.16
Plan II is better since the resulting EPS is higher than the other alternatives.
Answer:
c) a firm does not have sufficient time to change the level of use some of its inputs.
Explanation:
The definition of short-run in economics is not a term to be used for a specific certain period of time but it means that the period of time is too short that the firms cannot change the level they are using of some of their inputs or costs. It means they do have fixed costs they cannot change. For example, all machinery installed, a yearly rent paid, electricity or others that the firm cannot change unless there is sufficient time. In a short period of time, it will have those costs anyway. The firm cannot change the level of that input. And it is short run of at least one input. It may be many. But it is not necessary to have all inputs unchanged to consider that period of time as short-run.
However, firms can change level of inputs if they have more time. That is cost the long run. All costs are variable costs when we are in long run.
Answer: Maslow's hierarchy of needs
Explanation:
Maslow's hierarchy of needs is referred to as or known as a theory which was proposed by the American psychologist Abraham Maslow, that tends to put forth the notion/idea that individuals are usually/mostly motivated by the following five categories of need, i.e. safety, physiological, esteem, love, and also self-actualization.
Lower; unchanged
- Average total cost (ATC) in economics is calculated as total fixed and variable costs divided by the number of units produced. The normal shape of the average total cost curve is a U, meaning it drops, bottoms out, and then rises. The total cost of an organization is the sum of its fixed and variable costs.
- The vertical summation of AFC and AVC must be obtained in order to graph average total costs (ATC). Plot the points as shown on the left after adding the two at each output level. Because it is the result of adding the AFC and AVC curves, the ATC curve is higher than the other two. You can see that it is U-shaped, just like the AVC curve, on the left.
Thus this is the answer.
To learn more about curve, refer: brainly.com/question/25109150
#SPJ4
Answer:
True
Explanation:
the process of identifying and defining what actions are required to deliver a project's requirements