Answer:
10 days
Explanation:
The Critical Path Method is a method of managing activities in a project so as to maximize time. In the case of A, B and C activities, since they are connected with the same start-to-start and finish-to-finish, it means that the activities are linked and as such the duration of the project is 10 days since the last activity will take 10 days to finish.
The implication between SS and FF in the activities means that they start up at the same time in the CPM and while activity A ends at 5 days, C proceeds to 10 days.
Choose to do nothing about the problem is always a course of action.
Answer:
It will report 225,000
Explanation:
In the cash flow statment we focus on the cash received or used during the year. This is regardless of the gain or loss. When it was adquire the cash flow show use of cash for 75,000. Now, the land is sold. The company receive 225,000 cash. This amount is posted in the cash flow statement, as cash generated for investing activities.
<u>Resuming:</u>
On cash flow, you have to follow the money, not the gain or loss. If there is no cash receipt or disbursement, then you will not post anything.
The answer & explanation for this question is given in the attachment below.
Answer:
The answers are:
1) Expansionary fiscal policy: government policy that seeks to increase aggregate demand through higher government spending and/or lower taxes.
The government's deficit is increased by:
- Increasing government spending; the government will spend more money than what it collects in taxes.
- By lowering taxes; even if the government spending remains unchanged, if taxes are lowered the budget deficit will increase.
So any possible action that increases the deficit, will be considered an expansionary fiscal policy.
2) Government expansionary fiscal policy includes: D) increasing government spending, which increases the deficit.