The board's decision-making process is divided into two stages: communication and decision-making. Each director decides whether to incur a cost to communicate his information to others during the communication stage. At the decision-making stage, all directors take actions (e.g., vote) based on their private information and information inferred from the discussion, and the board makes a collective decision. Directors may have conflicts of interest and thus prefer a decision that is not in the best interests of the shareholders. Directors may also have a preference for conformity and thus incur a loss if their actions differ from those of other directors, such as voting differently than the majority.
Learn more about decision making here:
brainly.com/question/16407152
#SPJ4
Answer: Extra safety that is applied to a project immediately before the use of the constrained resource.(D)
Explanation:
Drum buffer can be explained as period of time that is used to safeguard the drum resource from the problems that occur from the drum operation.
The aim of the drum buffer effect is to provide a recheck of the work in order not to deviate from the real aim of the project. The buffer makes up for the process variation, and makes the project stable as it gives extra safety which is applied mmediately before using constrained resource.
Answer:
$10,800 underapplied
Explanation:
Calculation for If overhead is applied based on machine hours, the overapplied/underapplied overhead is:
Overhead machine hours=[($1,044,000/24,000)×23,600]-1,037,400
Overhead machine hours=($43.50 x 23,600) - 1,037,400
Overhead machine hours=$1,026,600- 1,037,400
Overhead machine hours= $10,800 underapplied
Therefore If overhead is applied based on machine hours, the overapplied/underapplied overhead is:$10,800 underapplied
Answer: They help a customer solve a problem without promoting a particular company's products
Explanation:
White paper is simply refered to as an authoritative report that is used in order to addresses certain issues that are deemed to be vital and also provide solution to such issues.
White papers gives awareness regarding particular products and it helps customer solve a problem without promoting a particular company's products.
Answer:
4 years
Explanation:
Payback period is the time in which a project returns back the initial investment in the form of net cash flow.
Initial Investment = $280,000
Net Income = $20,000
To calculate the net cash flows add bask the depreciation expense in Net income each year.
Depreciation = ($280,000 - $30,000) / 5 = $50,000
Net Cash Flow = $20,000 + $50,000 = $70,000
Payback period = Initial Investment / yearly cash flow = $280,000 / $70,000 = 4 years