Answer:
The correct answer is Option C.
Explanation:
In the indirect cash flows statement, there are 3 sections, namely: net cash flows from operating activities, net cash flows from investing activities and net cash flows from financing activities.
The items in the question only affect the first two. Under the net cash flows from operating activities, we need to subtract the gain realized from the disposal of the plant assets from net income, which is Sales proceed minus Net book value, i.e., $90,800 - ($904000- $843000) = $29,800.
The sales proceed is $90,800. This would be recognized as cash inflow under net cash flows from investing activities.
Answer:
Multiple choices below are missing:
A) purchase Bond A
B) purchase Bond B
C) purchase neither A nor B at this time
D) negotiate a higher rate on Bond A
The correct option is A,purchase bond A.
Explanation:
By purchasing Bond A,Lee is assured interest payment of 7.5% for a period of twenty years,hence the issuer cannot call the bond if interest rate drops by 2% in order to issue a lower interest-bearing bond which would be cheaper cost-wise.
However, if Lee purchases Bond B with current coupon of 8.25%,the interest is only guaranteed for a period of two years,since the issuer has the prerogative of calling back the bond after two years should interest fall in order to issue another bond that commands lower interest rate.
Answer:
PV= $620,921.32
Explanation:
Giving the following information:
Cash flow (Cf)= $100,000
Interest rate (i)= 7.25%
<u>First, we need to calculate the value of the investment at the moment of the first payment (five years from now). </u>To calculate the present value we need to use the following formula:
PV= Cf / i
PV= 100,000 / 0.1
PV= $1,000,000
<u>Now, the value today:</u>
PV= FV / (1 + i)^n
PV= 1,000,000 / (1.1^5)
PV= $620,921.32
Answer:
a. $13
b. $20,625 Unfavorable
Explanation:
a. Computation of overhead volume variance is shown below:-
Variable overhead rate = Variable overhead cost ÷ Expected standard hours
= $275,000 ÷ 25,000
= 11 direct labor hour
Fixed overhead rate = Productive capacity ÷ Expected standard hours
= $50,000 ÷ 25,000
= $2 direct labor hour
Total overheard rate = Variable overhead rate + Fixed overhead rate
= $11 + $2
= $13
b. The computation of overhead controllable variance is shown below:-
Variable overhead cost = Overhead rate × Standard hours
= $11 × 21,875
= $240,625
Fixed overhead cost = Overhead rate × Standard hours
= $2 × 21,875
= $43,750
Total overhead cost = $13 × 21,875
= $284,375
Actual result = $305,000
Variance = Actual result - overhead cost applied
= $305,000 - $284,375
= $20,625 Unfavorable
Working note:-
Standard direct labor hours = Actual units ÷ Standard hours
= 35,000 × 1.6
= $21,875
Standard units per hour = (Standard capacity × Expected production) ÷ Standard hours
= (50,000 units × 80%) ÷ 25,000 hours
= 1.6 units per hour