Answer:
A project is a combination of tasks that need to be finished to reach a specific, bigger goal. Since project tasks are not to be confused with the daily schedule of work, this is what differentiates a project from the routine tasks:
- <em>defined span</em> - while daily tasks are usually continuous by nature, project tasks are set in a specific time frame
- <em>project life cycle</em> - similar to the life cycle of a product, a project follows a similar curve that symbolizes the birth of the project, its maturity stage and its decline
- <em>defined goal/objective</em> - the completion of a project and its tasks has to be indicated by reaching a specific goal
- <em>cross-department teams </em>- project teams usually involve people from more business departments (marketing, HR, R&D...)
- <em>allocated resources</em> - while daily, continuous tasks usually source resources (financial, human...) from the firm directly, a project usually has a specifically assigned amount of allocated resources
Answer:
total predetermined overhead rate = $29.84 per machine hours
so correct option is C) $29.84 per machine-hour
Explanation:
given data
machine hours = 10,000
variable manufacturing overhead = $6.82
fixed manufacturing overhead = $230,200
to find out
predetermined overhead rate
solution
we know that here variable manufacturing overhead so
estimated fixed overhead rate will be
estimated fixed overhead rate = 
estimated fixed overhead rate = $23.02 per machine hour
and
total predetermined overhead rate is here
total predetermined overhead rate = $6.82 + $23.02
total predetermined overhead rate = $29.84 per machine hours
so correct option is C) $29.84 per machine-hour
Answer:
Option (b) is correct.
Explanation:
Given that,
Estimated total fixed manufacturing overhead = $121,000
Estimated direct labor-hours for the period = 10,000
Actual total fixed manufacturing overhead = $113,000
Actual total direct labor-hours during the period = 10,900
Predetermined overhead rate:
= Estimated total fixed manufacturing overhead ÷ Estimated direct labor hours
= $121,000 ÷ 10,000
= $12.10
Therefore, the predetermined overhead rate is closest to $12.10.
Answer:
Creative originator.
Explanation:
Tim is neither a project manager, because his web page was a personal project, and no other people were involved under his command, and his is not a godfather either.
He would be an entrepreneur if he had sold his web pages.
For the reasons above he is a creative originator: he essentially gave birth to a new work activity.