A tire company has plants in Chicago and Detroit. The Chicago plant can make 600 radial and 100 standard tires per day. The Detr

oit plant can make 300 radial and 100 standard tires per day. It costs $4,000 per day to operate the Chicago plant and $3,000 per day to operate the Detroit plant. The company has a contract to make at least 24,000 radial and 5000 standard tires.
How many days should each plant be scheduled to minimize operating costs?

Mathematics
2 answers:
sdas [7]3 years ago
5 0

Answer:

<u>To minimize operating costs, the Chicago plant should work 30 days and the Detroit plant should work 20 days </u>

Step-by-step explanation:

1. Let's review the information given to us to answer the question correctly:

Chicago plant can produce:

  • 600 radial and 100 standard tires per day
  • Cost of daily operation = $ 4,000

Detroit plant can produce:

  • 300 radial and 100 standard tires per day
  • Cost of daily operation = $ 3,000

Contract to make at least 24,000 radial and 5000 standard tires.

2. How many days should each plant be scheduled to minimize operating costs?

  • Let C to represent the number of days the Chicago plant to work
  • Let D to represent the number of days the Detroit plant to work

We can write our system of inequalities, this way:

100C + 100D ≥ 5,000

600C + 300D ≥ 24,000

Isolating C:

100C  ≥ 5,000 - 100D

C  ≥ 50 - D (Dividing by 10 at both sides)

Substituting C and solving for D in the 2nd inequality:

600(50 - D) + 300D ≥ 24,000

30,000 - 600D + 300D ≥ 24,000

-300D ≥ 24,000 - 30,000

-300D ≥ - 6,000

D ≥ -6,000/-300

D  ≥ 20

Solving for C in the 1st inequality:

100C + 100 * 20 ≥ 5,000

100C + 2,000 ≥ 5,000

100C ≥ 5,000 - 2,000

100C ≥ 3,000

C ≥ 3,000/100

C ≥ 30

In consequence, the total costs of operating the plants would be:

30 * 4,000 + 20 * 3,000

120,000 + 60,000 = $ 180,000

melomori [17]3 years ago
4 0

Answer:

To minimize the cost, the Chicago plant should run 30 days and the Detroit plant should run 20 days.

Step-by-step explanation:

This is a linear programming question, in which there is a function to optimize (minimize cost) and restrictions, all linear functions.

The objective function is Cost:

C=4000H+3000D

C: cost function

H: days of operation for Chicago plant

D: days of operation for Detroit plant

The restrictions are:

- Minimum requirements for radial tires:

600*H+300*D\geq24,000

- Minimum requirements for standard tires:

100*H+100*D\geq5,000

- Days are positive integers

H,D\geq0

We have 3 points in which 2 of the constraints are saturated. In one of this three points is the minimum cost.

We will evaluate them to find the minimum cost:

Point 1: H=0, D=80

C=4,000*H+3,000*D\\\\C=4,000*0+3,000*80=240,000

Point 2: H=50, D=0

C=4,000*H+3,000*D\\\\C=4,000*50+3,000*0=200,000

Point 3: H=30, D=20

C=4,000*H+3,000*D\\\\C=4,000*30+3,000*20=120,000+60,000=180,000

The third point minimizes the cost.

To minimize the cost, the Chicago plant should run 30 days and the Detroit plant should run 20 days.

You might be interested in
HELP PLEASE points Savanah is shopping for planters for her new plants. Which measurement should she use to determine how much s
Nady [450]

Answer:

D. Volume

Explanation:

  • volume - amount of space that a substance occupies

Here the substance is soil and planter will hold the specific volume of soil.

5 0
2 years ago
Jose worked 3 hours.<br> In a one day what fraction<br> of the day did he work?
Alexus [3.1K]
Since there are 24 hours in a day the fraction would be

3/24 but can be simplified to 1/8

The answer is Jose worked 1/8 of the day
7 0
3 years ago
Which of the following is the simplified form of fifth root of x times the fifth root of x times the fifth root of x times the f
JulsSmile [24]

Which of the following is the simplified form of [1] fifth root of x times the [2] fifth root of x times [3] the fifth root of x times [4] the fifth root of x?


That's


( \sqrt[5] x)^4 = x^{\frac 4 5}


That looks like the second choice.


6 0
4 years ago
Read 2 more answers
Help me please for the brailiest answer
Rom4ik [11]

Answer:

78, 1275

Step-by-step explanation:

a) 12th= 78

b) 50th=1275

5 0
3 years ago
How do I do these problems?
katen-ka-za [31]
For number 1) You need to get m alone, so you must add 4.4 to 2.6.
For number 2) Same thing as #1
For number 3) You must get c alone, you need to divide 10 by 2.5
For number 4) Same as #3
For number 5) You need to get t alone, so you must multiply both sides by 2.5
For number 6) Same as #5
5 0
3 years ago
Other questions:
  • If z varies directly with x and inversely with the cube of y, when x=8,y=2 and z=3, what is x when y=4 and z=9/32?
    15·1 answer
  • In a statistics course, a linear regression equation was computed to predict the final exam score from the score on the first te
    9·1 answer
  • I’m struggling with number 55 every time ive tried i don’t end up with the right answer
    14·1 answer
  • What is everyone being for halloween.
    15·2 answers
  • On Tuesday, the low temperature was 3 degrees colder than on Monday.
    6·1 answer
  • The pair of figures is similar. Find X. Round to the nearest 10th if necessary.
    5·2 answers
  • If you fint the correct answer i will give you thanks and mark you as brainlist
    5·1 answer
  • I don’t understand the second one please help
    11·2 answers
  • What is the volume of the object
    14·1 answer
  • Find the difference: <br><br> 60° 50' 40"<br><br> -30° 40' 50"
    6·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!