Answer: A - nominal wages are slow to adjust to changing economic conditions
Explanation:
In the short run, the costs of many of the factors used in the production process are fixed. For example labours wage is fixed for a number of years because of labour contracts. Also the raw materials used in the production process have long term agreements that fix their prices.
As a result of factors of production been fixed in the short run, when general price level rises and the cost of production remains constant, profit also rises.
Firms take advantage of this rise in price and increase production and the quantity of aggregate supply increases. This is why the short run aggregate supply curve is upward sloping.
Answer: B. The firm hires 45 workers and earns a $1,200.00 Economic Profit
Explanation:
If the Market Equilibrium rate is $105 then the company should hire 45 workers as shown in the table.
If they did that, revenue would be $7,425
Expenses would be wages and fixed costs:
= Wages + fixed costs
= (45 workers * wage rate) + 1,500
= (45 * 105) + 1,500
= $6,225
Economic profit would be:
= 7,425 - 6,225
= $1,200
The second firm finds that though demand is not perfectly elastic, it is now comparatively more elastic. The second firm marginal revenue will be more elastic and its profit maximizing price will be lower. A monopolist probably also considers in policies that indulgence monopolies since it gives them greater power. A monopolist has slight incentive to progress their product because customers have no replacements. Instead, the motivation is dedicated on defending the monopoly.
Answer:
b. risk management plan
Explanation:
this is true by definition, risk management involved forecasting risks, and laying out ways on how to manage them
- risk response plan is on how to reduce existing risks
- risk identification is to identify the risks of any open project
- risk balance plan is an analysis on how to maintain a balance on keeping safe and taking risks for greater benefit
Answer:
Shortening the duration of critical path tasks.
Explanation:
The critical path method is relevant for achieving effective project management. By visualizing the project's activities, it is possible to analyze the time needed to complete the tasks and avoid possible delays. The possibility of calculating the duration of completion time, the longest or the shortest, for each activity, also helps in reducing uncertainties, as it helps in reducing the unexpected surprises that may occur in the project.
This method also guarantees the advantage of helping to reduce project time by the possibility of visualizing which tasks can be reduced, as the method generates a greater understanding of the project's deadline as a whole, allowing a clearer view on which tasks can be changed and which should remain unchanged.