the work in an office take 150 hours to complete every week each person in the office works for 32 hours a week what is the smal lest number of people needed to complete the work
2 answers:
Divide the total number of hours by the number of hours each person can work to get 4.6 but since an office cannot employe 4.6 people the answer rounds up to five
Answer:
5 people
Step-by-step explanation: