Answer:
a. the difference between actual and budgeted fixed overhead costs.
Explanation:
As we know that
The variance is shows the difference between the actual amount and the budgeted amount or estimate amount
So, the total fixed overhead variance is the difference between the actual fixed overhead costs and the budgeted fixed overhead costs i.e to be fixed in nature
Hence, the first option is correct
Answer:
A) $560 million
Explanation:
First lets calculate the NPV of the cash stream by this investment,
PV Cash stream = Cash flow/ (r-g), where r = avg cost of capital and g = growth of the cash stream.
PV = 50 / (0.09 - 0.04) = $1000 million
We assume that external finance issuance costs are payable as a part of initial outlay of the project and so,
Total initial outlay = 420 + 20 = $440 million
NPV of the project then,
NPV = 1000 - 440 = $560 million
Hope that helps.
When the price level is falling to a negative zone, the economy is experiencing deflation, I believe.
Answer:
$42,240
Explanation:
The computation of the balance of the Accumulated Depreciation account at the end of 2019 is as follows;
But before that the depreciation rate is
= 1 ÷ 5 × 2
= 40%
For the first year, the depreciation expense is
= $66,000 × 40%
= $26,400
Now for the 2019, the depreciation expense is
= ($66,000 - $26,400) × 40%
= $15,840
Now the accumulated depreciation is
= $26,400 + $15,840
= $42,240
Answer:
$101,200
Explanation:
the cost of land = purchase price of the land + razing expenses - sales of salvaged materials + attorney's fees + broker's fees = $86,000 + $9,700 - $4,400 + $1,500 + $8,400 = $101,200
The cost of the driveways and parking lot are recorded separately (as land improvements), not under cost of land because they can be depreciated.
Architect's fees are generally included in the construction costs of the building, not in the land cost. The architect's fees are covered before the construction starts because you need the blueprints in order to start the construction.