Answer:
the price elasticity of supply is 0.555
Explanation:
The computation of the price elasticity of supply is given below:
= Percentage change in quantity supplied ÷ percentage change in price
= (25 - 20) ÷ (25 + 20) ÷ 2 ÷ (750 - 500) ÷ (750 + 500) ÷ 2
= 5 ÷45 ÷ 250 ÷ 125
= 0.555
Hence, the price elasticity of supply is 0.555
The same is relevant
Answer:
1. $275 million
Yes
2. 30%
Explanation:
Calculation for the NPV of the investment opportunity
NPV = –100 + 30/0.08
NPV= $275 million
Therefore the NPV will be $275 million
Yes, Based on the above Calculation they should make the investment
2. Calculation for IRR
IRR: 0 = –100 + 30/IRR
Hence,
IRR = 30/100
IRR = 30%
Therefore the IRR will be 30%
The IRR is great only in a situation where the cost of capital does not go beyond 30%.
Answer:
price variance $(22,800.00) UNFAVORABLE
Explanation:
std cost $6.00
actual cost $9.00
quantity 7,600
difference $(3.00)
price variance $(22,800.00)
We calculate the actual cost by dividing total cost by the lbs purchased:
68,400/7,600 = 9
Because the diference is negative, the variance is unfavorable.
Each pound cost more than it was planned.
Answer:
$50 and $2
Explanation:
The computation of the total revenue and the marginal revenue is shown below:
Total revenue is
= Price × quantity
= $2 × 25
= $50
And, the marginal revenue is received collected from one unit i.e price of the one units that equivalent to $2
Hence, we simply applied the above formula to determine the total revenue and the marginal revenue
Answer:
36.35%
Explanation:
According to the scenario, computation of the given data are as follows,
Sales = $78,400
Net income = $2,400
Cost of goods sodl = $43,100
Depreciation = $6,800
So, we can calculate the EBIT value by using following formula:
= EBIT ÷ Sales
= ($78,400 - $43,100 - $6,800) ÷ ($78,400)
= $28,500 ÷ $78,400
= 36.35%
Hence, the common-size statement value of EBIT is 36.35%