You must pay two types of taxes on earned income: Social Security/Medicare taxes (called FICA, OASDI, or payroll taxes) and income taxes. The payroll taxes that are withheld from your paycheck have two components.
Answer: $324,800
Explanation:
It is a general Principle that when calculating income tax expense, that the Extraordinary loss is treated separately because it is not a usual thing.
The income gained from changing the Accounting principle is not included as well.
The Taxable income to be recorded therefore is,
Taxable income = Income + Gain on disposal - Unusual loss (due to its infrequency)
Taxable income = 928,000 + 32,000 - 148,000
Taxable income = $812,000
Tax expense would therefore be,
= 812,000 * 40%
= $324,800
$324,800 is the amount of income tax expense Arreaga would report on its income statement.
A local Chamber of Commerce plans a seminar on “the social responsibility of business in our community.” What does that term reference?
( The expectations that the community imposes on firms doing business inside its borders.) correct answer of your question ✅
Answer:
$21,080.2
Explanation:
The price of the car will be the down-payment plus the future value of 375 paid each month for 5 years compounded monthly at 9.72%.
The formula for calculating future value is
PV = P × 1 − (1+r)−n
r
PV is $350
r is 9.72 % or 0.0972 % per year or 0.0081
t is five year or 60 months
FV = 350 x (1-(1+0.0081)-60
0.0081
Fv =350 x 1-0.61628715419
0.0081
FV =350 x( 0.38371284581/0.00810
FV =350 x 47.371956
FV =16,580.20
The value of the car = $4500 + 16,580.20
=$21,080.2
Answer:
The correct answer is letter "A": can be used to estimate the projected cost of completing the project.
Explanation:
The Cost Performance Index or CPI measures the projected cost of work completed compared to the current cost spent. The CPI represents a ratio of earned value to actual cost. If the CPI is greater than one, the project is under budget. When the CPI equals one the planned and actual costs are equal. If the CPI is higher than one, the project is over budget.