Answer:
Explanation:
To show that you have special skills and what your areas of expertise are.
Answer:
130%
Explanation:
Calculation for the predetermined overhead rate
Using this formula
Predetermined Overhead rate = Total Overhead Costs / Total direct materials costs
Let plug in the formula
Predetermined Overhead rate= $1,170,000 / $900,000
Predetermined Overhead rate=1.3*100
Predetermined Overhead rate= 130%
Therefore the Predetermined Overhead rate will be 130%
Answer:
A bad idea, as A2 is not on the critical path.
Explanation:
Critical path is a path which is the shortest path of doing the activity.
When an activity is in critical path, then there is a benefit of crashing it. Or if it is not the part of critical path then the benefit is to crash the activity and then apply the spare resources in some activity which is a part of critical path.
Thus, crashing A2 which is not a part of critical path and then not deploying the resources on to the activities of critical path will not provide for any benefit.
It is ultimately not a wise idea.
Answer:
Land Basis = $64,000
JM Basis = $5,000
Explanation:
As per the data given in the question,
Outside basis = $50,000
Carryover basis of land = $64,000
Land encumbered with mortgage = $30,000
Partnership interest = 50%
So her basis increased by = $30,000 × 50%
= $15,000
Total increased basis = $54,000 + $15,000
=$69,000
As per the following formula,
Basis left in partnership interest = Total basis - Carryover basis of land
= $69,000 - $64,000
= $5,000