1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Hunter-Best [27]
3 years ago
5

Evaluate the integral from negative infinity to infinity of xe^(x^(2)) dx

Mathematics
1 answer:
gogolik [260]3 years ago
8 0
\int{xe^{-x^2}}dx<span>

Let u=-x^2
du/dx=-2x
-du/2=x dx

</span>\int{xe^{-x^2}}dx=-1/2\int{e^u}du =- \frac{e^u}{2}+C=-\frac{e^{-x^2}}{2}+C

<span>When x approaches infinity (or minus infinity, since it is squared), e^(-x^2) approaches zero. So the answer is zero.</span>
You might be interested in
Given that x = 5.4 m and 0 = 26°, work out BC rounded to 3 SF.
bagirrra123 [75]

Answer:

BC ≈ 4.85 m

Step-by-step explanation:

Using the cosine ratio in the right triangle

cos26° = \frac{adjacent}{hypotenuse} = \frac{BC}{AC} = \frac{BC}{5.4} ( cross- multiply )

5.4 × cos26° = BC , then

BC ≈ 4.85 m ( to 3 s f )

4 0
3 years ago
Simplify and factor if necessary​
Dima020 [189]

Answer:

\frac{1}{x}

Step-by-step explanation:

\frac{3x - 12}{3x^{2}  - 12x}

\frac{3x - 12}{x(3x-12)}          Factor out x.

\frac{1}{x}                    Simplify.

4 0
3 years ago
A section of the dining room has 3 tables with 6 chairs at each table determine which expressions represent the situation and wh
tekilochka [14]

Do:

3x6

(3)(6)

6+6+6

Do not:

(3)-(6)

3/6

3+6

8 0
3 years ago
8 men will take 10 days to build a wall 150 metres long. After the men had started working for 6 days, they were told that the w
Mashutka [201]
First, find out how much each man works. If eight men take 10 days to build 150 m of wall, then that means that it takes 80 man days to build 150 m. One Man day is then 150÷80, in other words 1.875. If eight men have already been working for six days, then they have spent 8×6 man days, 48. 48 men days times 1.875 m of wall per man day equals 90 m of wall have been built. So, you have four days left to build the remaining 60 m of wall as well as 45 extra meters, in other words, 105 m total. 105 m divided by four days equals 26.25 m need to be built every day. Since one man builds 1.875 m of wall every day, to find the number of men total you need for the last four days, take 26.25÷1.875, Which equals 14 exactly. 14 is not the answer however, because it’s asking how many more men you need. Since you already have eight, you need six more to make 14

The answer is six more men
3 0
3 years ago
It costs the Quality company $.14 per mile to run its van. On Monday the van traveled 87.6 miles. How much did it cost to run th
Dafna1 [17]

Answer:

12.264

Step-by-step explanation:

* per would be saying the number of miles the van is running that day

.14 x 87.6

= 12.264

7 0
3 years ago
Other questions:
  • What can the answer be to this question?
    12·2 answers
  • How can we calculate the value of angle
    12·1 answer
  • so if i have 2 brands of fruit snacks and one of them costs 48.60 and the other brand is 40.15 which brand cost less per pound
    10·1 answer
  • Twenty-six students will attend the field trip to the career center. The cost to attend the career center is $x. Fifteen of thes
    7·1 answer
  • Rewrite the expression with the given base. <br><br> 16^x with a base of 2.
    6·1 answer
  • 32 is 90% of what number?
    15·1 answer
  • What is the function f(x) = 2(x + 6), find x if f(x) = 22
    8·1 answer
  • Laplace Transform of t ^{2}sin(2t)? ...?
    11·1 answer
  • 1/4 + 3/7<br> pls answer w workings out aswell!! thanks
    12·2 answers
  • What function is it ?! refer to photo. <br> 10 8<br> 5 4<br> 0 0<br> -5 -4
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!