Answer:
10 days
Explanation:
The Critical Path Method is a method of managing activities in a project so as to maximize time. In the case of A, B and C activities, since they are connected with the same start-to-start and finish-to-finish, it means that the activities are linked and as such the duration of the project is 10 days since the last activity will take 10 days to finish.
The implication between SS and FF in the activities means that they start up at the same time in the CPM and while activity A ends at 5 days, C proceeds to 10 days.
Answer:
- b. costs charged to departments.
- c. cost assignment and reconciliation.
- d. equivalent units of production
Explanation:
In Process costing, the company involved is producing a large amount of goods and services that are exactly the same. In order to assign costs therefore, the company will assign costs to all the products instead of individually.
Costs would be charged to various departments because they produce the goods so the entire department cost has to be assigned and reconciled with with the department that produce the goods. When the company only managed to partially complete the production of a good, they will still have to assign costs and so use equivalent units of production to do so.
Answer:
The correct answer is letter "D": Criterion-related validation.
Explanation:
Criterion-related validation is a reliability test that measures certain inputs in an attempt of predicting the performance of other groups of individuals who will be measured under the same criteria. The measure obtained in the first evaluation is called the predictor variable or estimator. Intelligence Quotient (IQ) tests are typical examples of the use of criterion-related validation methods.
<span>chairman Leonard Riggio takes the reins and assures employees of Barnes and Noble that he is going to do what he can to save the company. He tells them his idea that he should gather together private investors who can buy the company's brick and mortar stores which would make it become private. This is a great example of a leader.</span>