Number of labourers * Number of days worked = Total number of working days
Total number of working days to construct a 4km long road: 
Total mumber of working days to construct a 8km long road: 
Labourers: 20000 ÷ 80 = 250.
250 labourers are required.
Answer:14
Step-by-step explanation:
Yes, you can divide $5 by 2. There are 100 cense in a dollar, 500 in five dollars, if you divide 500 by 2 you get 250 cense, with each 100 cense equaling $1. You would have $2.50.
Also, you got number 5 wrong, it’s how far he’s gone, not how far he has left.
Answer:

Step-by-step explanation:
To find the scale factor of a dilation, we first find two corresponding sides. For example, the top edge of the black shape corresponds with the top edge of the purple shape. The top edge of the black shape measures 15 units while the top edge of the purple shape measures 3 units
Now, we divide the length taken from the figure by the length taken from the original shape. In this case, we divide the length of 3 by the length of 15.
3/15=
I hope this helps!