Answer:
The answers are:
- The CPI for 2009 is 100 (since it is the base year)
- The CPI for 2010 is 129.17
- The inflation rate for 2010 is 29.17%
Explanation:
<u>CPI basket for 2009</u>
- 6 razors x $20 per razor = $120
- 4 bottles of cologne x $30 per bottle = $120
The total value of the CPI basket for 2009 is $240
<u>CPI basket for 2010</u>
- 6 razors x $25 per razor = $150
- 4 bottles of cologne x $40 per bottle = $160
The total value of the CPI basket for 2010 is $310
- The CPI for 2009 is 100, since it is the base year
- The CPI for 2010 = (CPI basket 2010 / CPI basket 2009) x 100 = ($310 / $240) x 100 = 129.17
- The inflation rate for 2010 = [(CPI basket 2010 / CPI basket 2009) - 1] x 100 = (1.2917 - 1) x 100% = 29.17%
So you still have 60 points to go up. Every month is 3 more points. Divide 60 by 3 which will give you the number of months left before you reach your goal. 60/3= 20 months or 1 year and 8 months.
Answer:
Option (d) $5,549.96
Explanation:
Data provided in the question:
Annual payments = $800
Time, n = 12 years
Discount rate, r = 7% = 0.07
Now,
PV2 = Annual payments × ((1 - (1 + r)⁻ⁿ)) ÷ r ) × (1 + r)
= $800 × ( (1 - ( 1 + 0.07)¹²)) ÷ 0.07) × (1 + 0.07)
PV2 = $6,354.15
Therefore,
Present value today = PV2 ÷ (1 + r )²
= $6,354.15 ÷ (1 + .07)²
or
= $5,549.96
Hence,
Option (d) $5,549.96
Answer:
700 units
Explanation:
Calculation for the what the size of the order will be.
Using this formula
Unit to sell= Total additional fixed costs + desired profit / Contribution margin per unit=
Let plug in the formula
Units to sell=$550 + $850 / (8-6)
Units to sell= $1,400/2
Units to sell=700 units
Therefore the size of the order will be 700 units
The activity's crash cost per time unit is $30.
Crash cost per time unit equals the cost slope.
Cost slope equals rise/run; therefore (crash cost - normal cost)/(normal time - crash time)
or ($160 - $100)/(8 - 6)
= $30.
Activity crash costs are the costs associated with choosing a faster alternative to do work. Note that this is the full cost associated with the alternative approach, not the added cost. Therefore, the formula returns a value representing the accident cost per period.
A project crash means adding additional resources to speed up the project completion time. Lowering normals can crash your project. Completion times for critical activities called activity crashes. This can be achieved by having more resources to run them.
Learn more about crash activity here:brainly.com/question/18349575
#SPJ4