Answer:
make environmentalism profitable
Explanation:
THe Government´s effort on providing tax credits to those individuals that purchase electric vehicles is an attempt to make environmentalism profitable and encouraging the purchase and trade of electric vehicles that do not use fossil fuels to run and helo the environment, this is a very important effort by the government to make enviromentalism profitable for people and give an incentive to go green.
Answer:
The correct answer is the option D: Total project costs are the lowest.
Explanation:
To begin with, when it comes to the business field and the management area, the "project duration" refers basically to the characteristic that the project management has regarding the duration of it, very commonly expressed in terms of working units like hours, days, weeks, months or years for example. Moreover, there are three major types of project duration that are: "Estimated Project Duration", "Actual Project Duration" and "Remaining Project Duration". And to end up, the point where the duration of the project is opmital is when the total project costs are the lowest of all.
Answer:
Johnson & Johnson make $51,433.28 every 20 seconds
Explanation:
<u><em>The complete question is</em></u>
I'm playing a riddle game thing and one of the questions is
"How many dollars does Johnson & Johnson make every 20 seconds?"
I found that they make 81.1 billion dollars yearly, but I have no clue how to get it to 20 seconds.
Remember that
1 year=365 days
1 day=24 hours
1 hour=60 minutes
1 minute=60 seconds
so
Convert year to seconds

1 billion=1,000 millions
1 billion=1*10^9
81.1 billion dollars=81.1*10^9 dollars
we have

Convert to $/sec

Multiply by 20 sec

therefore
Johnson & Johnson make $51,433.28 every 20 seconds
Answer:
Total cost= $877,500
Explanation:
<u> First, we need to calculate the unitary variable cost:</u>
Unitary variable cost= 135,000 / 30,000= $4.5
Unitary variable cost= 180,000 / 40,000= $4.5
Unitary variable cost= 225,000 / 50,000= $4.5
<u>Now, the total cost for 35,000 hours:</u>
Total cost= Unitary variable cost*total number of hours + fixed costs
Total cost= 4.5*35,000 + 720,000
Total cost= $877,500
Answer:
The answer is A. $5,784,000
Explanation:
[(1.08)/(1.11)] -1 = -3.6%
Thus one year forward rate is 0.60*[1 +(0.036)] = $5784
$5784 * 10 000 000= <u>$5,784,000</u>