8

as a sales person which size hard disc would you recommend a customer who needs to use Microsoft PowerPoint application?

Computers and Technology
1 answer:
Anettt [7]3 years ago
4 0

Answer:

Not very big - maybe 64 GB or 128 GB

Explanation:

PPT doesn't take up much space

You might be interested in
......... mi2hej<br><br>ejid8eo19o1b2bxhxjxjdnneejk2929nr
Mila [183]

Answer:

hi  thsu si s5

Explanation:

brace use

5 0
3 years ago
Read 2 more answers
At what depth does an employer need to use a protection system to ensure the safety of workers in a trench or excavation?
nevsk [136]
Trench 4 foot or deeper and must be located 25 foot within eachother
3 0
3 years ago
Read 2 more answers
You have just performed a cpm analysis and have found that more than one path through the project network has zero slack values.
Alex787 [66]

Answer:

There are multiple critical paths

Explanation:

The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.

The essential technique for using CPM is to construct a model of the project that includes the following:

  •    A list of all activities required to complete the project (typically categorized within a work breakdown structure),
  •    The time (duration) that each activity will take to complete,
  •    The dependencies between the activities and,
  •    Logical end points such as milestones or deliverable items.      

Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).

considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.

5 0
3 years ago
Someone help me out eh?
Elodia [21]

Line 4

It should be font-size: 15px

Also there should be curly braces in line 5.

6 0
3 years ago
Read 2 more answers
What does a cascading style sheet resolve a conflict over rules for an element?
Margaret [11]
I Think The answer is d I hope it helps
4 0
3 years ago
Other questions:
  • How must you rect to a flashing<br> Yellow traffic light?
    9·1 answer
  • What network setting do i need for a workgroup?
    5·1 answer
  • In the context of Information Technology Infrastructure Library, _____ delivers information technology IT services on an ongoing
    14·1 answer
  • If Word finds a potential error in a document, a red, green, or blue wavy underline flags the problem. True or False
    6·1 answer
  • A server, also called a(n) _______________, operating system is a multiuser operating system because it controls a central compu
    6·1 answer
  • Explain briefly why every person in the world is not connected to the Internet.
    9·1 answer
  • Which line in the following program contains the header for the showDub function? 1 #include 2 using namespace std; 3 4 void sho
    9·1 answer
  • Mary can view the thumbnails of her presentation slides when she’s creating the slides which element of the programs interface i
    8·1 answer
  • Okay, guys, I know this one will be very hard however while trying to finish this assignment I got overwhelmed and lost by the s