Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
-20
Step-by-step explanation:
Replace X by 3
f(3) = -2(3)^2+ (3)-5 = -20
Answer:

Step-by-step explanation:
We need to find which statements are true.
Solution to find the same we will solve each statement and will conclude the same.
1. 
Now On solving we get;


So we can see that 0.70 > 0.66
Hence The given statement is False.
2. 
Now On solving we get;


So we can see that 0.5625 > 0.5
Hence The given statement is True.
3. 
Now On solving we get;


So we can see that 1.33 > 1.2
Hence The given statement is False.
4. 
Now On solving we get;


So we can see that 0.82 > 0.66
Hence The given statement is False.
Answer: 30 kilograms
explanation: Each 1000 grams converts to 1 kilogram