Answer:
b. No, the return is less than the required rate of 9%
Explanation:
Projected sale = 100000
Projected exp = 86000
Profit = 14000
Assets= 200000
Return on assets = 14000/200000 = 7%
Expected return = 9%
Hence, project should not be taken
Answer:
The answer is "Option b".
Explanation:
The Loanable funds are the amount of all the assets that individuals and companies have agreed to save and lend to creditors instead of for personal use, as an investment.
The earnings are also the foundation for supplying loanable funds. That request for credit funds is focused on lending. This relationship among saving provision and loan request decides its real rate as well as the sum of loans.
Answer:
The answer is B, C, and E.
Explanation:
Saw this post and one other neither had the correct answer so i figured i would help anyone out that needs the correct answer.
Answer:
C. Compensatory damages and consequential damages.
Explanation:
The reason is that the company can only sue Santa for its compensatory damage of paying 15% extra and consequential damages which are only claimable if the party to contract knows that not performing the contract will contribute to consequential damages which are here losses of sales which amount to 25% of sales.
Answer:
The correct answer is $9187.5.
Explanation:
According to the scenario, the given data are as follows:
Asset cost = $140,000
Residual value = $42,000
Life period = 8 years
So, Annual depreciation can be calculated by using following method:
Annual depreciation = ( Asset cost - Residual value) ÷ Life period
= ($140,000 - $42,000) ÷ 8
= $12,250
As depreciation is to be recorded till Dec.31
So, total time period = Apr - Dec = 9 months
So, Depreciation expense till Dec.31 = $12,250 × (9 ÷ 12)
= $9,187.5
Hence, Depreciation expense till Dec.31 is $9,187.5.