Answer:
Break-even point in total units= 951.7units
Explanation:
<em>Break-even point is the level of activity at which a firm must operate such that its total revenue will equal its total costs. At this point, the company makes no profit or loss</em>.
It is calculated using this formula:
<em>Break-even point (in units) = Fixed cost/ average contribution per unit</em>
<em> Blue Plaid</em>
Contribution per unit 43-30 = 13 52-45 = 7
<em>Average contribution per unit </em>
= ( (13× 4) + (7×5) )/9
= $ 9.66 per unit
<em>Break-even point in total units</em>
= $9200/$ 9.66
= 951.7units
Break-even point in total units= 951.7units
Answer:
E. have a sinking fund provision
Explanation:
Callable bonds are the one wherein the issuer/borrower has an option to redeem the bonds anytime after an initial stipulated period. In case of such bonds, if the issuer decides to redeem the bonds, the holders have to accept the redemption value.
Usually, when market rate of interest on such bonds falls below the coupon rate of such bonds, the issuer redeems such bonds. Thus, such bonds are beneficial to the issuer.
Call protection refers to the period within which such bonds cannot be called or redeemed.
Sinking fund provision refers to transferring a portion of money during the duration of such callable bonds to a separate reserve known as sinking fund, which is created for the purpose of redemption of funds. So when such bonds are to be called, the total money transferred to sinking fund reserve would be raised and used for payment to bondholders.
Creation of such a reserve helps the issuer avoid the pressure of lump sum payment as periodically funds are set aside for the purpose of redemption.
Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.
The step of the process of control that is illustrated in this question is measuring performance.
<h3>What is the process of control?</h3>
This is the process that is done in order to make sure that the performance of a business is carried out effectively using a series of steps.
The measurement of performance is done to check out how the business is doing, It helps to see if the objectives are being met.
Read more on the control process here:brainly.com/question/14051119