Answer:
100
Explanation:
Goal programming is an optimization technique that allows for multiple, normally conflicting objectives and then attempts to solve each goal sequentially to a satisfactory level. In goal programming, differential variables are being used.
Since the goal programming problem had two goals. Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory. The optimal solution to this problem resulted in a profit of $2,300 and no idle time
This means that goal number 2 was achieved since the optimal solution resulted in no idle time. But goal number 1 was not achieved because a profit of $2300 was achieved in the solution instead of $2400.
Therefore, the value for the objective function for this goal programming problem = 2400 - 2300 = 100
Are you sure about the name of this guy? I have found much information about Jan Kulczyk who was <span>Poland's richest individual. If you want, I may personally drop you a link about him.
</span>
Answer: Price Ceilings
Price Ceilings are usually controlled by the Government and their main use is to keep prices up. Sometimes a customer will switch to other goods and that person that wants there item bought the price will get lower to attract more customers. In this case, they want to keep the prices from falling - therefore, it would be Price Ceilings.
Answer:
Two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.
According to Goldratt, two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Answer:
.793
Explanation:
Formula
.032=.7^2*.17^2+.3^2*.23^2+2(.7)(.3)(.17)(.23)p
.032=.0142+.0048+.0164p
.032-.0142-.0048=.0164p
.0164p=.013
p=.013/.0164
p=.793