Well for question a.) the answer is 3.5 we find this by taking 6-2.5=3.5 th rule is to add 3.5
The answer is the option a. Count the days it takes the cats to finish a 3.5 - pound bag of cat food, divide 3.5 by that number of days; multiply the result by 365<span>. When you divide 3.5 pounds by the number of days, you get the average number of pounds that the cats eat per day. Then, when you multiply the average number of pounds that the cats eat per day times 365, you get the number of pounds that the cats eat in 365 days, which is the same that saying in a year. </span>
Answer: The perimeter is 20 cm
Step-by-step explanation: The top and bottom are same length, so 6+6, and the sides are the same length, so 4+4 don’t forget it’s cm and it becomes 20 cm.
PERIMITER = ADDING ALL SIDES
AREA = MULTIPLYING
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.