Tasya [4]
3 years ago
14

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three acti

vities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project.
Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going? (Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.)
Business
1 answer:
adell [148]3 years ago
4 0

Answer:

1. schedule variance = -$52,500

2. SPI = 0.65

3. CPI = 0.56

Explanation:

to get the solution, we calculate for BRWS and BRWP

first we calculate the budgeted revenue of the work scheduled for each activity using this formula:

<u>budgeted</u><u> </u><u>revenue</u><u> </u><u>*</u><u> </u><u>planned</u><u> </u><u>completion</u>

A = 25,000 x 100percent

= $25000

B = 150,000 x (25/30) percent

= $125000

C = 50000 x 0percent

= 0$

total = $25000+$125000+$0

= $150000

Next we calculate budgeted revenue of work performed (brwp)

<em>calculated using this formula</em>:

<u>budgeted revenue x actual </u><u>completion</u>

A = 25000 x 90percent

= 22500 dollars

B = 150000 x 50percent

= $75000

C = 50000 x 0%

= $0

total = 22500 + 75000 + 0

= $97500

<u>1</u><u>.</u><u> </u><u>schedule</u><u> variance</u><u> </u><u>=</u><u> </u><u>BRWP </u><u>-</u><u> </u><u>BRWS</u>

<u>=</u><u> </u>$97500 - $150000

= -$52500

<em>we </em><em>have</em><em> a</em><em> </em><em>negative</em><em> </em><em>schedule</em><em>,</em><em> </em><em>telling</em><em> </em><em>us </em><em>that </em><em>the </em><em>project</em><em> </em><em>is </em><em>behind</em><em> </em><em>schedule</em>

<em>2</em><em>.</em><em> </em><u>schedule</u><u> </u><u>performance</u><u> </u><u>index </u><u>=</u><u> </u><u>revenue</u><u> </u><u>of </u><u>work </u><u>performed</u><u> </u><u>divided </u><u>by </u><u>revenue</u><u> of</u><u> work</u><u> </u><u>schedule</u>

<u>=</u><u> </u>97500/150000

= 0.65

3. <u>cost price index = revenue of work performed divided by actual revenue</u>

= 97500/175000

= 0.56

4. <u>how </u><u>the </u><u>project</u><u> </u><u>is </u><u>going</u><u>:</u>

the schedule performance index (SPI) is 0.65 which is less than 1. this is to say that the project is doing better than planned revenue when we talk of revenue

You might be interested in
What is a project milestone in business
Solnce55 [7]

Answer:

A project milestone is a task that shows an important achievement in a project. The milestones should represent a clear sequence of events that incrementally build up until your project is complete.

Explanation:

3 0
3 years ago
The loan department of a financial corporation makes loans to businesses. The costs of processing these loans are often several
Ket [755]

Answer:

Operation costing

Explanation:

Operating costing is the combination of the job costing and the process costing. In this the cost are received for each and every operation rather for each and every process

Since in the given situation it is mentioned that they need some outside services like legal services etc so here the costing system that used for the loan department is operation costing

3 0
3 years ago
Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing overhead:
Dahasolnce [82]

Answer:

the  overhead cost assigned to Job 971 is $1,020

Explanation:

The computation of the overhead cost assigned to Job 971 is shown below:

= Budgeted Machine overhead cost ÷ Number of set up

= $13,200 ÷ 390

= 34

Now the overhead cost assigned is

= 30 setups × 34

= $1,020

hence, the  overhead cost assigned to Job 971 is $1,020

Therefore the last option is correct

3 0
3 years ago
Note that common work styles are listed toward the top, and less common work styles are listed toward the bottom.
AURORKA [14]

Answer:

leadership

dependability

analytical thinking

Initiative

Self control

Explanation: These are the common needed work styles by Nursery and Greenhouse managers currently.

3 0
3 years ago
The term​ "crowding out" refers to a situation​ where: A. Fed policy increases interest rates and decreases private investment.
Neporo4naja [7]

Answer:

The correct option is : C. Government spending increases interest rates and decreases private investment.

Explanation:

The term crowding out refers to a situation of increased interest rates and a decrease in private investment. The government spending is known as the crowding out investments, as it demands more loanable funds and thus leading to increase in the interest rates and a reduction in the private investment spending.

5 0
3 years ago
Read 2 more answers
Other questions:
  • Which of the following statements is not correct?
    7·1 answer
  • A town has many fast food restaurants, which charge an average of $6 for a hamburger. However, one fast food restaurant charges
    15·1 answer
  • The value of a listed put option on a stock is lower when _______________. I. the exercise price is higher II. the contract appr
    15·2 answers
  • Suppose a producer charges $20 for a new toy. At this price, the producer supplies more toys than people demand, so there is a(n
    12·2 answers
  • If a population grows by 3 percent each year the growth of the population is
    15·1 answer
  • What are some examples of a consumer in an economic system?
    9·1 answer
  • After graduating from high school, Shawn took out a loan to help pay for college. Now, four years later, Shawn has graduated fro
    9·2 answers
  • "Wants" as an economic concept includes only goods and services that consumers need but cannot afford to buy. both material and
    11·1 answer
  • Kevin bought 205 shares of Intel stock on January 1, 2020, for $52 per share, with a brokerage fee of $105. Then, Kevin sells al
    6·1 answer
  • When firms set a single price for all customers, regardless of how much they buy or under what conditions they make their purcha
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!