Answer:
B. Causes of variability
Explanation:
Inventory reduction via Just in time is a technique that aligns raw material orders from suppliers directly to production schedules. It helps in reducing inventory costs. It increases efficiency and reduces waste as goods are only received when the organization using JIT needs them for operations. In JIT, production period is short, warehouse need is minimize thus reducing costs. Also, it becomes of useful tool in identifying causes of variability. It reduces variability caused by both internal and external factors. Variability are normal deviation from the most efficient and optimum process.
Hello. You forgot to show the calculations made by Nico and Lorena. The calculations are shown in the attached figure.
Answer:
Nico is correct because he knew -4/5 is equal to -4/5.
Explanation:
As you can see in the image below, Nico and Lorena had to solve the expression (2) x (1/6) x (-4/5).
In this case, the correct resolution is Noco's resolution, since it has the following resolution steps:
2x1x (-4) / 1x6x5 =
-8/30 =
-4/15
Answer:
c) 5 days, 7 workers
Explanation:
The longest task is Task-1 which takes 5 days.
All the tasks are parallel. So, the length of the project should be 5 days. The resources employed are just the total of all the tasks i.e. 2+2+1+1+1 = 7.
5 days, 7 workers
<span>Assif Mandvi's imitation of an american answering a call for "tech support" was an example of ethnocentrism. Ethnocentrism can be defined as the belief that one's own ethnic group is superior to other groups. Ethnocentrism is also the tendency to view other cultures from one's own perspective, instead of objectively.</span>