The answer is -2.25 bye!!!!!!!!!!!!!!!!!!!!!!!!!1
Answer:
it took longer to get to the beach
Step-by-step explanation:
they drove to the beach for 3 hours and 25 minutes and it took 55 minutes less to get home
Answer:
i know what you can do
go to jupiter to get more stupider
Step-by-step explanation: #6 yr old burns
#ameture hour
400-5x greater than or equal to 250
-400. -400
———————————————————-
-5x greater than or equal to -250
——. ——
-5. -5
X is less than or equal to 50
*sorry no greater than and equal to key so...
Answer:
(a) 2min/15units
(b) 1min/20units
(c) The bottleneck stage is cutting. The process capacity is 450units/hour
(d) The capacity of the new employee should be 1unit/2sec. The process capacity will increase four times
Step-by-step explanation:
(a) Cycle time for stage cutting for 2 employees = 16sec/2units × 1min/60sec = 2min/15units
(b) Cycle time for stage sealing for 1 employee = 3sec/1unit × 1min/60sec = 1min/20units
(c) Process capacity of stage cutting = 15units/2min × 60min/1hour = 450units/hour
(d) If the capacity of the new employee is 1unit/2sec, the process capacity = 1unit/2sec × 3600sec/1hour = 1800units/hour. The process capacity increases 4 times (1800/450 = 4)