1. Right to safety
2. Right to education
3. Right to be heard
4.Right to choose
5.Right to healthy environment
6.Right to education
7.Right to basic needs
8.Right to representation
Just pick four, I thought id list them all so you could pick what ones you wanted to use AND know your rights! Im taking the same test, good luck!
Answer:
25 seats
Explanation:
Calculation to determine By how many seats should Super Discount overbook the fight
First step is to calculate the Critical ratio=
Using this formula
Critical ratio=Cu/Cu+Co
Where,
Cu represent cost of underetimating the demand =$134
Co represent the cost of overestimating the demand $263
Let plug in the formula
Critical ratio=$134/$134+$263
Critical ratio=$134/397
Critical ratio=0.3375
Second step is to find the z-score that yields a p-value of 0.3375 using excel's normsinv() function which gives us -0.4193.
Now let determine how many seats should Super Discount overbook the fight
Numbers of seats to overbook the fight=35+ (-0.4193 x 24)
Numbers of seats to overbook the fight= 35 - 10.0632
Numbers of seats to overbook the fight = 24.9368
Numbers of seats to overbook the fight = 25
(Approximately)
Therefore the numbers of seats that super discount airlines should overbook the flight is 25 seats.
Answer:
The answer is: D) is a more convenient location to hold the trial.
Explanation:
A change of venue happens when a case is transferred from a court in one location to a court in a different location. It can be requested if it is convenient for the parties in a lawsuit.
In this case both Eduardo and Delia live in Georgia, so if a trial is held there, they would need to travel and probably hire local lawyers which can be time consuming and expensive. Eduardo can argue that by holding the case in Georgia benefits both Delia and him.
The project duration in a network diagram can be determined by the largest value of the variable earliest finish time associated with the critical path.
In project management, the critical path is the longest series of tasks to be done in order to complete a project. The tasks on the critical path, if delayed, the entire project will be delayed. Finding the critical path is a vital step as it accurately estimates duration of a project completion, identifies risks and constraints, prioritizes tasks and finds task dependencies. Gantt charts can be used to calculate the critical path.
Earliest finish time is an important variable in the calculation of the critical path. Earliest finish time of a task is the earliest possible time during which the task can be completed. To calculate project duration along a critical path, the largest value of the variable earliest finish time is considered.
It is because the critical path is the longest path that gives the longest duration of the project completion. But the result of the critical path gives the shortest time required to finish the project.
You can learn more about critical path at
brainly.com/question/15091786
#SPJ4