Answer:
B
Step-by-step explanation:
DSAWFYYAGGDSFHDSGFH FHSDGJHFGSDHJ SDFJKSHFJSH B HGJJHGJ
Answer: $3.20
Step-by-step explanation:
SI = p *r * t
= 5.93 * 0.06 * 9
= 3.20
Answer:
21, 23, 25
Step-by-step explanation:
Ok, so this one may seem a little tricky, so I'll try to explain it as best as I can. :)
So because they are consecutive odd numbers, that means they are odd numbers that are one after the other. This means each number is 2 apart from the next. So by using this, we know that there is a difference of 6 between the highest and lowest number. Now let's try and make an equation:
3o + 6 = 69
Now in order to get O by itself we have to subtract 6 from both sides:
3o = 63
Now we just have to divide by three on both sides:
o = 21
So now, we know that the lowest number is 21, but we have to add 2 to get 23, and then another 2 to get 25.
Hope this helps :)
Answer:
both
Step-by-step explanation:
angle ABC is an isoceles triangle since BC and AB are equal. If you look at the other two triangles they are also isoceles because they have 2 equal sides as well.
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days