Answer:
The NPV = $1578.185602 rounded off to $1578.19
As the NPV is positive, the project should be accepted.
Explanation:
The Net Present Value or NPV is a tool used to evaluate projects. It is used with various other tools to decide whether to undertake a project or not. To calculate the Net Present Value or NPV, we take the present value of the cash inflows provided by the project and deduct the initial cost of the project. If the NPV is positive, we should proceed with the project and vice versa.
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial Cost
Where,
- CF1, CF2, ... represents cash flow in Year 1, Year 2 and so on.
- r is the required rate of return
NPV = 3200 / (1+0.17) + 3200 (1+0.17)^2 + 3200 (1+0.17)^3 +
3200 (1+0.17)^4 + 5700 (1+0.17)^5 - 9800
NPV = $1578.185602 rounded off to $1578.19
Answer:
The correct answer is a. production points outside the production possibility frontier are unattainable
Explanation:
Production possibility frontier graph is attached.
The production possibility frontier shows the possibilities of trade off between two products. The trade off in this frontier use all the resources available. So it is impossible to reach a point outside the frontier, there are not enough resources.
Answer: "building footprint" .
_____________________________________