Answer:
$10,800 underapplied
Explanation:
Calculation for If overhead is applied based on machine hours, the overapplied/underapplied overhead is:
Overhead machine hours=[($1,044,000/24,000)×23,600]-1,037,400
Overhead machine hours=($43.50 x 23,600) - 1,037,400
Overhead machine hours=$1,026,600- 1,037,400
Overhead machine hours= $10,800 underapplied
Therefore If overhead is applied based on machine hours, the overapplied/underapplied overhead is:$10,800 underapplied
Answer:
The right solution is "$966.27".
Explanation:
Given values are:
Coupon rate,
= 10%
Par value,
= $1000
Yield of maturity,
= 12%
then,
Coupon will be:
=
=
= ($)
Now,
The present value of coupon will be:
=
By putting the value, we get
=
=
=
= ($)
The present value of par value will be:
=
=
= ($)
hence,
The price of bond will be:
=
=
= ($)
Answer:
Dr Cash $332,775
Cr Bonds payable $290,000
Cr Premium on bonds payable $42,775
Explanation:
Preparation of the journal entry to record the issuance of these bonds. Assume the bonds are issued for cash on January 1, 2017
Based on the information given the journal entry to record the issuance of these bonds will be:
Dr Cash ($290000/100*114.75) $332,775
Cr Bonds payable $290,000
Cr Premium on bonds payable ($332,775-$290,000) $42,775
(To record issuance of bonds)
Answer:
$6,300( unfavorable)
Explanation:
The relative variance of the utility expense is the budgeted utility expense minus the actual utility expense.
Budgeted utility expense=$38,700
actual utility expense=$45,000
relative variance for utility expense=$38,700-$45,000
relative variance for utility expense=-$6300
Note that this has to do with a cost, hence, the lesser your actual cost is compared to the budgeted cost, the better.
Since actual cost is higher than budgeted, it means more money than expected was spent, all in all, it is an unfavorable variance.
Answer:
A. $60,000 U
Explanation:
Given that
Budgeted fixed cost = 540,000
Actual fixed cost = 600,000
Recall that,
fixed overhead flexible-budget variance = Actual amount - standard (budgeted) amount
Thus,
Variance = 600,000 - 540,000
= $60,000 Unfavorable
It is unfavorable because the actual cost is higher than the budgeted cost. When actual cost is less than budgeted cost, it is favorable.