Answer:
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:
C. 9.
Explanation:
The implication is that the standard deviation of the critical path is the sum of the standard deviations of the four activities on the critical path. This sums to 9 days (1 + 2 + 4 + 2), implying that the critical path varies from the mean days of critical path activities by 9 days plus or minus.
According to jennifer Jacquet's, shaming does not work when:
- The majority of other people does not follow that specific action (for example if most people within a certain society does not feel shame being naked in public, it is very unlikely you could shame an individual to do so)
- There is no punishment associated with the shame
- There is other option that balance the action associated with the shame
Think of competitors that sell the same thing, for example Pacific Coffee or Pretz.
Answer: Strategic Analysis.
Explanation: Strategic analysis is the process that firms use to study and understand the many different aspects of their competitive environment. This analysis involves the process that focus on researching an organization’s business environment within which it operates. It is an essential tool in formulating strategic planning for decision making and smooth working of the business organization.
Strategic analysis refers to the process of conducting research on a company and its operating environment within which its operates to formulate a strategy. Strategic analysis helps define a strategy that will help stand out from the competitors and to also remain competitive. Another important function of strategic analysis is the prediction of future events and the planning of an alternative approach if the first fail to deliver.